Map Update History

The Map Update Log below tracks and describes updates to the conceptual map beginning in January 2024. 

Map Update by County

Table Description:

  • Date: Month of map update.
  • County: Location of the map update.
  • Update Description: Summary of map update.
  • Partner: Name of network partner.
DateCountyUpdate DescriptionPartner
2024-01-29AlamedaApproximately 1-mile route extension on Warm Spring Blvd in Fremont to reflect the lease agreement accuratelyBoldyn
2024-01-29Contra CostaApproximately half-mile route extension near Hillcrest Community Park in Concord to reflect the joint build agreement accuratelyArcadian
2024-01-29El DoradoApproximately 3 miles of duplicate line removed on highway 49, south of Placerville, to reflect the joint build agreement accuratelyCVIN
2024-01-29HumboltApproximately half-mile route extension in Trinidad, west of highway 101, to reflect the joint build agreement accuratelyVero
2024-01-29KernApproximately 2.5-mile route adjustment on highway 166 to reflect the lease agreement accuratelyCVIN
2024-01-29KernApproximately half-mile route removed on California Street in Maricopa to reflect the lease agreement accuratelyCVIN
2024-01-29KingsApproximately 3 miles of duplicate lines removed on highway 43, near Hanford to reflect the lease agreement accuratelyCVIN
2024-01-29Los AngelesApproximately half-mile route extension in Boyle Heights to reflect the joint build agreement accuratelyArcadian
2024-01-29Los AngelesApproximately half-mile route on highway 105 near LAX shifted to off state highway Caltrans
2024-01-29NapaApproximately half-mile route removed as part of route adjustment in downtown Napa with no impact to network or coverage of the areaCaltrans
2024-01-29NevadaApproximately 14.5-mile route moved from interstate highway 80 east of Truckee to the Nevada border due to prohibitive permitting issuesArcadian
2024-01-29PlacerApproximately 1.5-mile route extension on highway 28, in King’s Beach to complete the network to the border of California and NevadaArcadian
2024-01-29RiversideApproximately 1-mile route extension between highway 215 and Murrieta Road for network functionalityCaltrans
2024-01-29SacramentoApproximately 8-mile route adjustment on highway 99, east of Sacramento Airport, moving 3 miles east to expedite permittingCVIN
2024-01-29SacramentoApproximately 1-mile route aligned on highway 99 in downtown Sacramento reflect the joint build agreement accurately Caltrans
2024-01-29San BernardinoApproximately 5-mile route adjustment from interstate highway 15 to interstate highway 40 in Barstow to reflect the joint build agreement accurately Arcadian
2024-01-29San JoaquinApproximately 1-mile route adjustment on interstate highway 5 and interstate highway 205 south of Lathrop to reflect the lease agreement accuratelyCVIN
2024-01-29San Luis ObispoApproximately 5 miles of spur on highway 46 east of Shandon removed, no impact to network or coverage of the areaCaltrans
2024-01-29SiskiyouApproximately half-mile route extension on highway 96 in Somes Bar to reflect the joint build agreement Siskiyou Tel
2024-01-29SiskiyouApproximately half-mile route extension on highway 96 in Happy Camp to accurately reflect the joint build agreement Siskiyou Tel
2024-01-29SonomaApproximately 6.5-mile route extension on highway 12, between highway 116 and highway 101, west of Santa Rosa for network enhancementCaltrans
2024-01-29SutterApproximately 2.5-mile route adjustment from highway 99 east to Levee Road, south of Yuba City to reflect the lease agreement accuratelyCVIN
2024-01-29TehamaApproximately 1.5-mile route aligned in downtown Red Bluff with no impact to network or coverage of the area. Partner to connect parallel routesCaltrans
2024-01-29TulareApproximately 3 miles of duplicate lines removed on Aveue 304 and Road 64, west of Visalia, to reflect the lease agreement accuratelyCVIN
2024-01-29TuolumneApproximately 1 mile of duplicate lines removed on Parrotts Ferry Road, northwest of Columbia, to accurately reflect the joint build agreementCVIN
2024-01-29TuolumneApproximately half mile of duplicate lines removed on Morning Star Lane in Sonora to reflect the joint build agreement accuratelyCVIN
2024-01-29TuolumneApproximately 1.5 miles of duplicate lines removed on highway 108 east of Jamestown to reflect the lease agreement accuratelyCVIN
2024-01-29VenturaApproximately half-mile route extension on highway 33 connecting to highway 101 in Ventura to reflect the joint build agreement accuratelyCaltrans
2024-02-26RiversideApproximately 37 route miles previously identified as Caltrans construction were reclassified to a lease through CDT’s ongoing data reconciliation process. There are no updates to routes, existing contracts, or costs. Lumen
2024-02-26San DiegoApproximately 29 route miles previously identified as Caltrans construction were reclassified to a lease through CDT’s ongoing data reconciliation process. There are no updates to routes, existing contracts, or costs. Lumen
2024-02-26VariousAs part of CDT’s ongoing data reconciliation process, approximately 53 route miles were adjusted Statewide for a total of 10,566 miles. There are no updates to routes, existing contracts, or costs. N/A
2024-02-26VariousThe Lumen contract spans approximately 1,896 miles. Of this, 710 miles are being leased, and 1,186 miles are a joint build project (using existing conduit). Initially, all miles are combined and reflected as a lease. To facilitate accuracy and transparency, CDT has updated its website to break out these two components. The 1,186 leased miles have been reclassified as joint build.Lumen
2024-03-25Los AngelesApproximately 2 route miles along Highway 101 and Interstate 110 are being adjusted to the east side of Interstate 110. This adjustment removes 1 mile of route without impacting area network coverage.Caltrans
2024-03-25Los AngelesApproximately 1 route mile near Los Angeles International Airport (LAX) is being adjusted from Imperial Highway to El Segundo Boulevard due to prohibitive permitting issues. This adjustment removes 1 mile of route without impacting area network coverage.Caltrans
2024-03-25ShastaApproximately 3.5 route miles on Interstate 5 are shifting from southbound to northbound lanes to avoid railroad crossings. This adjustment has no impact on area network coverage.Caltrans
2024-04-29TulareApproximately 28 route miles on Highway 99 and SR 190 are being shifted off State highways due to prohibitive permitting issues. No net mile changes or impact on area network coverage.CVIN
2024-05-28MercedApproximately 11-mile route adjustment on I-5 and SR 152. This engineering allows us to complete by the federal deadline. This adjustment results in a nominal change of less than a mile.CVIN
2024-06-24HumboltThe route on SR 255 is reclassified to a lease (TPN299) through CDT’s ongoing data reconciliation process. There are no updates to existing contracts or costs.Caltrans
2024-06-24San BernardinoAs a result of a streamlining opportunity, approximately 6-mile route was removed from Interstate 10 and 1-mile route added to Interstate 215. This was in order to avoid toll road project which would delay MMBN installation.Caltrans
2024-06-24San FranciscoDue to reconstruction, approximately 2-mile route on Townsend Street shifted to Brannan Street. No net mile changes or impact on area network coverage.Lumen
2024-07-22Multiple (statewide)The following miles (by county) were reallocated from Caltrans construction to joint build partnerships to reach all FFA grant locations within existing funding: Imperial 69 miles; Lake 80 miles; Lassen 39 miles; Los Angeles 105 miles; Plumas 19 miles; Riverside 30 miles; San Bernardino 45 miles; San Diego 3 miles; Tehama 59 miles; Ventura 33 miles; Yolo 4 miles.Anticipated Partnerships
2024-07-22Multiple (statewide)The following miles (by county) were reallocated from Caltrans construction to one or more lease partnerships to reach all FFA grant locations within existing funding: Kern 12 miles; San Luis Obispo 64 miles; Santa Barbara 82 miles.Anticipated Partnerships
2024-07-22Multiple (statewide)The following miles (by county) were reallocated from Caltrans construction to one or more lease partnerships to reach all FFA grant locations within existing funding: Del Norte 30 miles; Humboldt 17 miles.Ytel
2024-08-26AmadorApproximately 1 mile was shifted from Hanford Street to Amador Road in Amador City to avoid local site conditions.CVIN
2024-08-26AmadorGIS performed data reconciliation to reflect routes along the county border more accurately resulting in 5 miles increased.CVIN
2024-08-26ButteApproximately 1 mile was shifted west from State Route 99 to a local roads in Chico, CA.CVIN
2024-08-26ButteApproximately 3 miles were added along State Route 162 based on revised Federal Funding Account (FFA) grant applicant data.Anticipated Partnership
2024-08-26El DoradoGIS performed data reconciliation to reflect routes along the county border more accurately resulting in 6 miles increased.Caltrans
2024-08-26KernApproximately 1 mile was shifted from State Route 184 to Panama Road and South Fairfax Road in order to avoid Right-of-Way permitting constraints.CVIN
2024-08-26KernApproximately 1 mile was shifted from Sycamore Road to Meryers Street, El Camino Real, and Tejon Highway to avoid Right-of-Way permitting constraints. CVIN
2024-08-26KernApproximately 1 mile was shifted from Bussell Road to Mayer Avenue to avoid Right-of-Way permitting constraints.CVIN
2024-08-26KingsApproximately 6 miles were shifted from Highway 198 and Highway 41, to Jackson Ave, 18th Ave, Laurel Ave, and 22nd Ave in the Stratford area to avoid Right-of-Way permitting constraints.CVIN
2024-08-26MarinApproximately 3 miles were added to State Route 1 based on revised FFA grant applicant data.Caltrans
2024-08-26MontereyGIS performed data reconciliation to reflect routes along the county border more accurately. No overall mile change.CVIN
2024-08-26San BenitoGIS performed data reconciliation to reflect routes along the county border more accurately resulting in 7 miles increased.CVIN
2024-08-26San Luis Obispo GIS performed data reconciliation to reflect routes along the county border more accurately resulting in 1 mile increased.
CVIN
2024-08-26San Luis Obispo Approximately 17 miles were added along E Highway 46 based on revised FFA grant applicant data.Anticipated Partnership
2024-08-26Santa BarbaraGIS performed data reconciliation to reflect route along county border more accurately. No overall mile change.CVIN
2024-08-26Santa ClaraApproximately 1 mile was removed along State Route 152 and State Route 101 to avoid Right-of-Way permitting constraints.CVIN
2024-08-26Santa ClaraGIS performed data reconciliation to reflect routes along the county border more accurately resulting in 6 miles decreased and added to San Benito.CVIN
2024-08-26SutterApproximately 2 miles were shifted from State Route 99 and Natomas Road, to Catlett Road and Pleasant Grove Road to avoid delay due to conflicting construction efforts.CVIN
2024-08-26TuolumneApproximately 4 miles added on Highway 108 due to local site conditions and to reach FFA grant applicant data.Caltrans
2024-08-26VariousBased on GIS data reconciliation activities, approximately 1 mile was added statewide for Lumen (Joint Build). There are no updates to routes, existing contracts, or costs.Lumen
2024-09-30Contra CostaApproximately 2 miles were removed along Arnold Industrial Way and State Route 242 to reflect joint build agreement accurately. This adjustment removes approximately 2 miles without impacting area network coverage or cost. Arcadian
2024-09-30Kern, San Luis Obispo, Santa BarbaraApproximately 158 miles were reallocated from Anticipated Partnerships (Lease) to CVIN due to contract amendment.CVIN
2024-09-30Placer, Sacramento, SutterRoute shifted from Natomas and East Levee Roads to Pleasant Grove Road, Riego Road, and along Locust Road. This was in order to avoid federal permitting challenges. This adjustment adds a net of ~2 mile without impacting area network coverage or costs.CVIN
2024-09-30SacramentoApproximately 2 miles was added along Truxel Road and Gateway Park Boulevard in order to connect to a major data center. Arcadian
2024-09-30SacramentoRoute shifted from River Road and along State Highway 160 to Interstate 5 in order to avoid Right-of-Way and permitting challenges. This adjustment adds a net of ~7 miles to the route.Arcadian
2024-09-30ShastaRoute shifted from local roads near Terry Lake Road and Bunch Grass Lookout Road, to State Highway 299. This was in order to avoid private or inaccessible property. This adjustment removes ~1 mile of route without impacting area network coverage or costs. CVIN
2024-09-30VariousApproximately 380 miles were reallocated from Anticipated Partnerships (Joint Build) to American Dark Fiber due to newly signed partnership.American Dark Fiber
2024-09-30VariousApproximately 53 miles were reallocated from our joint build and lease partnerships to Caltrans construction to reflect the way in which hub miles are being delivered.Caltrans
2024-10-28AllNo route adjustments during this month.All
2024-11-25AmadorApproximately 2 miles were added along State Route 88 between Jackson Street and Pine Grove Street, in order to avoid Right-of-Way permitting challenges.CVIN
2024-11-25HumboldtApproximately 3 miles along State Route 96 were reallocated from Caltrans construction to Ytel lease partnership due to contract amendment.Ytel
2024-11-25RiversideApproximately 18 miles were added along State Route 74 due to in-flight and substantially complete Caltrans Construction miles previously not reflected on the map.Caltrans
2024-11-25ShastaApproximately 10 miles were added along Interstate 5 due to in-flight and substantially complete Caltrans Construction miles previously not reflected on the map.Caltrans
2024-11-25VenturaApproximately 3 miles along West Telegraph Road were reallocated from Caltrans construction to a joint build partnership due to network realignment.Anticipated Partnerships (Joint Build)
2024-11-25YubaApproximately 1 miles were added along State Route 65 to reflect updated engineering work. This adjustment does not impact area network coverage.CVIN
2024-12-26AlamedaApproximately 2 miles were added along State Route Near 66th Ave and San Leandor Street to reflect updated hub engineering work. This adjustment does not impact area network coverage.Caltrans
2024-12-26HumboldtApproximately 10 miles were added along State Route 101 due to alignment with Karuk Tribe’s design of joint build partnership. This adjustment does not impact area network coverage or costs.Vero Networks
2024-12-26HumboldtRoute shifted along State Route 101 from Cresent City to south of the Oregon border in order to avoid Right-of-Way permitting challenges. This adjustment adds a net of ~2 miles without impacting area network coverage or costs.Karuk
2024-12-26HumboldtApproximately 0.5 miles were added along State Route 200 and State Route 299 to reflect updated hub engineering work. This adjustment does not impact area network coverage. Caltrans
2024-12-26Los AngelesApproximately 2 miles were added along State Route 605 due to hub optimization. This adjustment does not impact area network coverage.Caltrans
2024-12-26PlacerApproximately 1 mile was added along Interstate 80 (I-80) north of State Route 49 to reflect updated hub engineering work. This adjustment does not impact area network coverage.Caltrans
2024-12-26PlumasApproximately 0.5 miles were added along State Route 36 from Chester to Lassen County border to reflect updated engineering work. This adjustment does not impact area network coverage.American Dark Fiber
2024-12-26RiversideApproximately 1 mile was removed along State Route 74 due to hub optimization. This adjustment does not impact area network coverage.Caltrans
2024-12-26RiversideApproximately 3 miles were added along Dillon Road and State Route 86 due to hub optimzation. This adjustment does not impact area network coverage. Caltrans
2024-12-26RiversideApproximately 0.5 miles were added along Case and Mapes Roads due to bridging segment optimzation. This adjustment does not impact area network coverage.Lumen (Lease)
2024-12-26SacramentoHub location shifted from along State Route 99 to along State Route 104 due to hub optimization. This adjustment adds ~0.5 mile of route without impacting area network coverage or costs.Caltrans
2024-12-26San BernardinoApproximately 1 mile was added along West Slover Avenue and South Riverside Avenue due hub optimization. This adjustment does not impact area network coverage.Caltrans
2024-12-26San Luis ObispoApproximately 2 miles were added along State Route 46 to reflect updated engineering work. This adjustment does not impact area network coverage. American Dark Fiber
2024-12-26ShastaApproximately 1 mile was removed along State Route 89 and State Route 299 due to hub optimization. This adjustment does not impact area network coverage.Caltrans
2024-12-26StanislausApproximately 1 mile was removed along W Maint Street and Lander Ave due to hub optimization. This adjustment does not impact area network coverage.Caltrans
2024-12-26TrinityApproximately 1 mile was removed along State Route 299, east of Juction City, to reflect updated hub engineering work. This adjustment does not impact area network coverage. Caltrans
2024-12-26VariousApproximately 2 miles were added to various counties to reflect updated hub engineering work. This adjustment does not impact area network coverage or overall project costs.Various
2024-12-26VariousApproximately 2 miles were added to various counties to reflect updated engineering work. This adjustment does not impact area network coverage or overall project costs.Various
2024-12-26VariousApproximately 0.5 miles were removed along State Route 88 to reflect updated interconnection engineering work. This adjustment does not impact area network coverage or overall project costs.Various
2024-12-26VariousApproximately 1 mile was removed as a result of hub location refinement. This adjustment does not impact area network coverage or overall project costs.Various
2024-12-26VariousGIS performed data reconciliation to reflect routes along the county borders more accurately resulting in a ~0.5 mile reduction. This adjustment does not impact area network coverage or overal project costs.Various
2025-01-27HumboldtApproximately 46 miles were reallocated from Anticipated Partnerships (Joint Build) to Karuk due to newly signed partnership.Karuk
2025-01-27HumboldtApproximately 1 mile was returned to Anticipated Partnerships (Joint Build) to reflect route alignment and realignments. This adjustment does not impact area network coverage or costs.Anticipated Partnerships (Joint Build)
2025-01-27Los AngelesApproximately 75 miles were reallocated from Anticipated Partnerships (Joint Build) to Gateway Cities due to newly signed partnership.Gateway Cities
2025-01-27Los AngelesApproximately 1.3 miles were returned to Anticipated Partnerships (Joint Build) to reflect route alignment and realignments. This adjustment does not impact area network coverage or costs.Anticipated Partnerships (Joint Build)
2025-02-24AlamedaRoute shifted towards the west in San Leandro from State Route 238 and State Route 580 to 4WD Road to reflect updated engineering work. This adjustment added a net of ~1 mile without impacting area network coverage or costs.Caltrans
2025-02-24ButteApproximately 3 miles were reallocated from Anticipated Partnership (Lease) to Anticipated Partnerships (Joint Build) due to contract amendment.Anticipated Partnership (Joint Build)
2025-02-24KingsIn Lemoore, the CVIN route was extended from State route 41 approximately 1.7 miles to West Hills College . This adjustment did not impact area network coverage or costs. Lumen-IRUwOption
2025-02-24Los AngelesApproximately 12.8 miles were reallocated from Anticipated Partnerships (Joint Build) to LA Bureau of Street Lighting due to contract amendment.LA Bureau of Street Lighting
2025-02-24OrangeApproximately 1 mile was added in the Tustin along East Edigner Avenue and State Route 55 to reflect updated engineering work. This adjustment does not impact area network coverage.Lumen Technologies (Joint Build)
2025-02-24Santa BarbaraApproximately 2.3 miles were reallocated from CVIN to Anticipated Partnerships (Joint Build) due to contract amendment.Anticipated Partnership (Joint Build)
2025-02-24ShastaApproximately 2 miles were reallocated from Caltrans to Anticipated Partnerships (Joint Build) due to contract amendment.Anticipated Partnership (Joint Build)
2025-02-24VariousApproximately 2 miles were removed from various counties to reflect updated engineering work. This adjustment does not impact area network coverage or costs.American Dark Fiber
2025-02-24VariousApproximately 6.8 miles were added to various counties to reflect updated engineering work. This adjustment does not impact area network coverage or costs.CVIN
2025-02-24VariousApproximately 31.6 miles were reallocated from CVIN to Anticipated Partnership (Lease) due to contract amendment.Anticipated Partnership (Lease)
2025-02-24VariousApproximately 8.2 miles were added to various counties to reflect updated engineering work. This adjustment does not impact area network coverage or costs.Anticipated Partnership (Lease)
2025-02-24VariousApproximately 0.5 mile were added from various counties to reflect permitting issues or updated engineering work. This adjustment does not impact area network coverage or overall project costs.

*This is a rollup of changes across the state with each change being from 0.01 to 0.49 miles.
Various
2025-03-31MendocinoApproximately 0.5 miles were removed along State Route 1 from Point Arena to the Navarro River to reflect updated engineering work.This adjustment does not impact area network coverage or costs.Caltrans
2025-03-31San BernardinoApproximately 0.7 miles were added along Interstate 15 from Mariposa Road in Oak Hills to Stoddard Wells Road to reflect updated engineering work. This adjustment does not impact area network coverage or cost.Arcadian
2025-03-31VariousApproximately 1.2 miles were removed from various counties to reflect updated engineering work. This adjustment does not impact area network coverage or overall project costs. *This is a rollup of changes across the state with each change being from 0.01 to 0.49 miles.Various
2025-04-28AlamedaApproximately 487 miles were reallocated from Caltrans construction to American Dark Fiber in the following counties: Alameda 0.5 miles; Butte 23.3 miles; Calaveras 4.7 miles; Contra Costa 15.2 miles; Del Norte 15.8 miles; El Dorado 16 miles; Fresno 25.8 miles; Lassen 3.9 miles; Marin 9.8 miles; Mariposa 31.6 miles; Mendocino 132.7 miles; Orange 15.4 miles; Plumas 13.9 miles; Riverside 0.5 miles; San Bernardino 0.5 miles; San Diego 0.2 miles; Santa Clara 19.2 miles; Santa Cruz 2.5 miles; Siskiyou 44.1 miles; Sonoma 69.0 miles; Tuolomne 42.7 miles.

This adjustment does not impact area network coverage or overall costs.
American Dark Fiber
2025-04-28AlamedaApproximately 19 miles along State Route 1 from the Oregon Border to Crescent City were reallocated from Caltrans construction to one or more lease partnerships. This adjustment does not impact area network coverage or costs.American Dark Fiber
2025-04-28El DoradoApproximately 1 mile in Crescent City along the Redwood highway from East Washington Boulevard to 5th Street were reallocated from Caltrans construction to Ytel. This adjustment does not impact area network coverage or overall costs.American Dark Fiber
2025-04-28LassenApproximately 14.5 miles were adjusted in the following counties as a result of the contract ammendment reallocating Caltrans construction miles to American Dark Fiber: Butte 1 mile; Calaveras 0.3 miles; Contra Costa -0.4 miles; Del Norte 0.5 miles; El Dorado 2.1 miles; Fresno -0.8 miles; Lassen 0.2 miles; Marin -0.1 miles; Mariposa 4.5 miles; Mendocino 0.2 miles; Orange 4.1 miles; Plumas 0.2 miles; Santa Clara 2.9 miles; Santa Cruz 0.3 miles; Siskiyou 5.8 miles; Sonoma 1.5 miles, Tuolomne -0.6 miles.

These adjustments reflects updated design work from the partner and does not impact area network coverage or overall costs.
American Dark Fiber
2025-04-28Los AngelesApproximately 2 miles were added along various routes in Central Los Angeles to reflect updated engineering work. This adjustment does not impact area network coverage.Gateway Cities
2025-04-28Los AngelesApproximately 6.6 miles were adjusted in the following counties to reflect updated engineering work:

Contra Costa 1.0 miles; El Dorado 0.1 miles; Humboldt -2.9 miles; Los Angeles 0.5 miles; Marin 0.3 miles; Mendocino 0.5 miles; Nevada 1.2 miles; Placer 0.2 miles; Sacramento 1.3 miles; San Bernardino 2.5 miles; San Jaoquin 0.1 miles; Santa Clara 1.1 miles;
Sonoma 0.5 miles.

This adjustment does not impact area network coverage or overall costs.
Arcadian
2025-04-28MendocinoApproximately 4 miles along State Route 1 from Simpson Lane to Cypress Street were reallocated from Caltrans construction to one or more joint build partnerships. This adjustment does not impact area network coverage or overall costs.American Dark Fiber
2025-05-26VariousApproximately 1 mile was removed from various counties to reflect updated engineering work. This adjustment does not impact area network coverage.Karuk
2025-05-26VariousApproximately 0.5 mile was removed from various counties to reflect updated engineering work. This adjustment does not impact area network coverage.YTel
2025-05-26VariousApproximately 1 mile was added to various counties to reflect updated engineering work. This adjustment does not impact area network coverage. *This is a rollup of changes across the state with each change being from 0.01 to 0.49 miles.CVIN
2025-05-26VariousApproximately 0.5 mile was added to various counties to avoid permitting issues. This adjustment does not impact area network coverage.Gateway Cities
2025-05-26VariousApproximately 20 miles were reallocated from Anticipated Partnership (Joint Build) to American Dark Fiber due to contract amendment.American Dark Fiber
2025-05-26VariousApproximately 5 miles were removed from various counties to reflect updated engineering work. This adjustment does not impact area network coverage.American Dark Fiber
2025-05-26VariousApproximately 1 mile was removed from various counties to reflect updated engineering work. This adjustment does not impact area network coverage.Lumen-IRU
2025-05-26VariousApproximately 2 miles were removed from various counties to avoid permitting issues and reflect updated engineering work. This adjustment does not impact area network coverage.CVIN
2025-05-26VariousApproximately 10 miles were added to various counties to reflect updated engineering work. This adjustment does not impact area network coverage.CVIN
2025-06-30FresnoApproximately 0.5 miles of planned network were removed northeast of the intersection of State Route 180 and Belmont Avenue to reflect updated engineering work. This adjustment does not impact area network coverage.Anticipated Partnerships (Lease)
2025-06-30KernApproximately 1 mile was added within the City of Wasco, extending along McCombs Road and between North Palm Avenue and Central Valley Highway to reflect updated engineering work. This adjustment does not impact area network coverage.Anticipated Partnerships (Lease)
2025-06-30VariousMinor adjustments totalling approximately 2 miles were removed across various counties to reflect updated engineering work. This adjustment does not impact area network coverage. This is a rollup of changes across the state with each change being from 0.01 to 0.49 miles.Various
2025-07-28VariousApproximately 0.1 miles were added due to engineering work across various counties. These adjustments do not impact area network coverage. This is a rollup of minor changes across the state.Various
2025-08-25AlamedaApproximately 2 miles were added along State Route 580 between State Route 680 in Dublin and State Route 238 in San Lorenzo to reflect updated engineering work. This adjustment does not impact area network coverage.Boldyn Networks (Boldyn)
2025-08-25ButteApproximately 3 miles were added along State Route 162 between Oro Dam Boulevard and the junction with State Route 70 near Lone Tree Road and Powerhouse Hill Road in Oroville to reflect updated engineering work. This adjustment does not impact area network coverage.CVIN
2025-08-25KingsApproximately 1 mile was removed along Lacey Boulevard between Hanford and Lemoore to reflect updated engineering work. This adjustment does not impact area network coverage.CVIN
2025-08-25ModocApproximately 3 miles were added along State Route 139 through Tulelake, from County Road 121 to the Modoc/Siskiyou County line to reflect updated engineering work. This adjustment does not impact area network coverage.CVIN
2025-08-25SiskiyouApproximately 2 miles were added along State Route 161 through Dorris, from the Siskiyou/Modoc County line to Richardson Road to reflect updated engineering work. This adjustment does not impact area network coverage.CVIN
2025-08-25SonomaApproximately 1 miles were added along State Route 161 through Dorris, from the Siskiyou/Modoc County line to Richardson Road to reflect updated engineering work. This adjustment does not impact area network coverage.American Dark Fiber (ADF)
2025-08-25TulareApproximately 2 miles were added along the Tipton-Porterville corridor (to South Jaye Street) to reflect updated engineering work. This adjustment does not impact area network coverage.CVIN
2025-08-25VariousApproximately 2 miles were added due to engineering work across various counties. These adjustments do not impact area network coverage. This is a rollup of minor changes across the state.Various
2025-08-25YubaApproximately 1 mile was added along Highway 70, from Olivehurst to the Highway 65 junction at the Placer County boundary near Wheatland, to reflect updated engineering work. This adjustment does not impact area network coverage.CVIN
2025-09-29AmadorApproximately 0.5 mile was removed along Clinton Road, between Contini Mine Road and Mission Boulevard/State Route 88 intersection, to reflect updated engineering work. This adjustment does not impact area network coverage.CVIN
2025-09-29Del NorteApproximately 3 miles were added along State Route 197 and 199, extending from U.S Highway 101 near Cresent City to Darlingtonia, to reflect updated engineering work. This adjustment does not impact area network coverage.American Dark Fiber (ADF)
2025-09-29Del NorteApproximately 19 miles were broken out from Anticipated Partnerships (Lease) to Tolowa Dee-ni’ Nation partner due to contract amendment.Tolowa Dee-ni’ Nation
2025-09-29KingsApproximately 7 miles were added along State Route 41, extending from Lemoore westward to Interstate 5, to avoid permitting challenges. This adjustment does not impact area network coverage.CVIN
2025-09-29Los AngelesApproximately 0.5 mile was added from North Industrial Parkway in San Bernadino to Cogswell Road in El Monte, to reflect updated engineering work. This adjustment does not impact area network coverage.Anticipated Partnerships (Joint Build)
2025-09-29Santa BarbaraApproximately 32 miles were broken out from Anticipated Partnerships (Lease) to CVIN partner due to contract amendment.CVIN
2025-09-29Santa CruzRoute shifted in Watsonville, from South Green Valley Road to Porter Drive, to avoid permitting challenges. This adjustment added a net of ~3 miles without impacting area network coverage.CVIN
2025-09-29VariousApproximately 0.1 mile was removed to reflect updated engineering work across various counties. These adjustments do not impact area network coverage. This is a rollup of minor changes across the state.Various
2025-09-29YubaRoute shifted along State Route 70, from the Yuba-Butte County line south to the town of Linda at the State Route 20 intersection, to avoid permitting challenges. This adjustment added a net of ~3 miles without impacting area network coverage.CVIN